More troubles for BRT Peshawar project
Auditor General raised serious objections on BRT Peshawar
BRT Peshawar
was launched by the PTI KPK government as a flagship project before the general
elections 2018. The PTI provincial government has so far given many deadlines
for the completion of this project- but work is still going on. Many reports have
appeared in the media in which serious allegations were raised regarding faulty
design-expensive contracts and corrupt practices.
Now the
latest report of Auditor General of Pakistan (AGP) has raised the similar kind
of objections and pointed out irregularities.
The report pointed out that project’s planning was faulty and
construction work started in the absence of detailed engineering design.
This report has
shown that how the PTI government led by then Chief Minister KPK Pervaiz
Khattak started this important project without proper planning and preparation.
The government tried to complete the project in haste to get political advantage.
So many
technical issues were ignored in the execution of the project. The poor
planning and execution increased the total cost of the project. This report is
a clear charge sheet against the KPK government. The billions of rupees were
wasted and lost in the process. Many irregularities were committed due to haste
and poor planning.
The report
also pointed out that Asian Development Bank (ADB) had well in time identified
the risk that “political pressure to fast-track the project due to General
Elections 2018 will undermine both design and implementation of the project”.
The report
said, “With regard to the projects undertaken during the BRT Corridor
Preliminary Design and later on during the Detailed Engineering Design (DED)
stages, the audit observation was justified to term all expenditure wasteful
which resulted from lack of vision in the planning process.”
The report
pointed out unauthorized variations of Rs10.4 billion; loss of Rs200 million
due to payment of excess quantity of pile concrete. The loss of Rs 54.8 million
due to non-recovery of cost of dismantled material; payment of Rs 95 million as
salaries without approved pay structure; non-deposit of profit worth Rs 12
million into government treasury earned from saving account.
The unauthorized
payment of Rs 45 million to officers; interest worth Rs 12 million earned not
reflected in financial statement; contradiction in approved PC-I and business
model regarding annual subsidy of Rs 1.6 billion; wasteful expenditure of Rs 716
million on beautification, construction of roads and electrification.
The
premature procurement of BRT buses spending US$ 7.9 million; the warranty
period of these buses may expire as well as wear and tear will occur with no
fare revenue from these buses; loss of Rs 10 million due to depreciation of
buses waiting to be brought on road; construction supervision contract worth
Rs 615 million and US$1.97 million awarded without fulfilling the criteria for
performance assessment; non-implementation of penalty/liquidated damages worth
Rs1.9 billion etc.
An email extract of December 2016 shared with the auditors
indicated that ADB did not want the DED (Detailed Engineering Design) to be
developed on the basis of the preliminary design.” Lack of planning was further
evident from the fact that in its aide-memoire dated 25th September 2017, the
ADB had stated that while the DED was still under-preparation, the provincial
government somehow got the original PC-I approved well below the ADB estimates
of USD 587 million.
Likewise the preliminary design, the report
said, the DED consultants were also not allowed appropriate completion time
which is normally allowed for detailed engineering designing of the projects of
such magnitude.
The DED
contract starting in Feb 2017 was supposed to be completed in Feb 2018 but due
to unnecessary urgency imposed on the project, the civil works were initiated
in November 2017 when complete designs were not even available.
According to
the loan agreement between the ADB and the government, the project is expected
to be completed by June 2021. However, unrealistic completion deadlines were
given in disregard of the ADB apprehensions. The initial cost of the project as
approved was Rs49.34 billion which was later revised to Rs 66.4 billion.
PTI leaders
including Prime Minister Imran Khan take credit to bring in a clean
administration and government. He also claimed to have maximum transparency in
the projects. This report by AGP needs serious consideration from PM Imran
khan. An independent inquiry must be conducted to fix the responsibility of
losses and wastage of billions of rupees.
Khalid Bhatti
Post a Comment